- Details
Early warnings
This series of articles has already emphasised that the NEC4 suite works on the basis of collaboration and pro-active contract management. The Early Warning provisions reinforce this approach.
What are the key features of the Early Warning provisions?
The NEC4 ECC includes an early warning mechanism (Clause 15) which is of mutual benefit to the parties under the standard form to control cost, time and quality management. The early warning provisions echo the principles of mutual trust and co-operation by encouraging the parties to find solutions collaboratively and timeously when there is the risk of:
- a price increase;
- a delay to project completion or to meeting a Key Date; or
- the project not being completed to meet requirements for the works to be fully operational upon completion.
Early warnings are managed via an Early Warning Register. This is essentially a risk register. The Project Manager prepares this at the beginning of the project and organises an early warning meeting soon afterwards. Subsequent early warning meetings take place on a regular basis once the project is underway otherwise upon instruction by either the Contractor or the Project Manager as issues arise. Sub-Contractors and others may be asked to attend an early warning meeting if their input is required to resolve an issue.
At an early warning meeting, those in attendance discuss:
- how to avoid or reduce the effect of matters which may have a detrimental impact on the project; and
- solutions to issues and consider the allocation of relevant actions to tackle the risks.
The Project Manager is responsible for updating the Early Warning Register to record decisions made at an early warning meeting and then circulates the Early Warning Register to the Contractor within a week of the meeting. If a decision results in the need for a change to the Scope, the Project Manager issues an instruction for that change when they issue the revised Early Warning Register. The Early Warning Register can also be amended to remove items which no longer present a time, cost or quality risk to the project. It should also identify who is responsible under the contract for actions relating to matters recorded on the Early Warning Register and steps to be taken to deal with matters.
The parties should also include potential early warning matters in the Contract Data when they enter into the contract to the extent that factors can be identified at that stage. These matters will then be included in the Early Warning Register from the outset so that the parties can review each item at early warning meetings for any impact on the project. The Early Warning Register should also note how the risks identified might be avoided or reduced.
Key takeaways:
- The early warning provisions can be used to proactively manage cost, time and quality issues under the NEC4 ECC.
- The Early Warning Register is a live document. It is important to keep it up-to-date and to work through issues collaboratively as the project progresses.
- You should refer to the contractual provisions in full and the Early Warning Register associated with your project if you experience any issues.
For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email
|
Click here to view our archived articles or search below.
|
|
ABOUT SHARPE PRITCHARD
We are a national firm of public law specialists, serving local authorities, other public sector organisations and registered social landlords, as well as commercial clients and the third sector. Our team advises on a wide range of public law matters, spanning electoral law, procurement, construction, infrastructure, data protection and information law, planning and dispute resolution, to name a few key specialisms. All public sector organisations have a route to instruct us through the various frameworks we are appointed to. To find out more about our services, please click here.
|
|
OUR RECENT ARTICLES
August 26, 2026
Local Government Reorganisation and rethinking corporate structuresIs now the time to rethink your corporate structures? Peter Collins looks at the benefit for local authorities undergoing local government reorganisation in reviewing their arrangements. Local Government Reorganisation is often viewed as a process of transition. It can also be…
August 25, 2026
Local Government Reorganisation and the shareholder roleIn the fourth instalment in his five-part series, Peter Collins looks at who will hold the shareholder role after vesting day. One question often receives less attention than it deserves during Local Government Reorganisation. Once the new authority comes into existence, who…
August 25, 2026
Local Government Reorganisation and liabilitiesPeter Collins sets out the liabilities councils going through reorgansiation cannot afford to overlook. Corporate structures can sometimes create the impression that assets, contracts and liabilities sit at arm's length from the council itself. In reality, understanding exactly…
August 21, 2026
Reforms to the NSIP Regime (and Beyond…)James Goldthorpe, Emyr Thomas and Alastair Lewis set out where the government’s Nationally Significant Infrastructure Projects (“NSIPs”) reforms have reached, the implications of the changes made to date and how the latest consultation “beyond NSIPS” could allow the government…
|
|
OUR KEY LOCAL GOVERNMENT CONTACTS
|
||
|
Partner 020 7406 4600 Find out more |
||
|
Partner 020 7406 4600 Find out more |
||
|
Rachel Murray-Smith Partner 020 7406 4600 Find out more |
||
|
|
||
|
Jo Pickering Partner 020 7406 4600 Find out more |
||
|
|
||
|
Emyr Thomas Partner 020 7406 4600 Find out more |
||
|
|
||
|
Gemma Duncan Partner 020 7406 4600 Find out more |
||
|
|
||
|
Simon Kiely Partner 020 7406 4600 Find out more |
||





Catherine Newman