- Details
Liquidated damages and termination
Clare Mendelle, Francesca Gallagher and James Goldthorpe provide an outline of the Supreme Court's recent decision in Triple Point Technology vs PTT Public Company Limited.
On 16 July 2021, the Supreme Court handed down its long-awaited judgment in the case of Triple Point Technology vs PTT Public Company Limited[1]. This important decision for the construction industry has confirmed the accepted position that while liquidated damages (LDs) cease to accrue on termination any accrued rights to LDs survive termination.
As a reminder, LDs are a pre-determined level of damages to which one party is entitled in the event of certain specified breaches occurring. In the context of construction contracts, LDs clauses are frequently used to incentivise the contractor to complete on time, providing for a fixed rate to be paid to the employer for each day or week that works are late.
Background
In 2013, Triple Point (the Contractor) and PTT entered into a contract (the Contract) under which Triple Point was to provide software and software implementation services to PTT. The works were divided into two Phases, and Triple Point was to be paid in instalments on completion of nine separate milestones.
The Contract included an LDs clause which provided:
“If Contractor [Triple Point] fails to deliver work within the time specified and the delay has not been introduced by PTT, the Contractor shall be liable to pay the penalty at the rate of 0.1% of undelivered work per day of delay from the due date for delivery up to the date PTT accepts such work…” (emphasis added).
Works proceeded slowly and Phase 1 was completed 21 weeks late. PTT accepted these works and paid Triple Point for Phase 1, but refused to pay invoices in relation to Phase 2 as the relevant milestones had not been reached. Subsequently, in May 2014, Triple Point suspended work on the basis of non-payment and left the site. PTT said this was wrongful termination (a repudiatory breach) and so terminated the Contract in March 2015.
Proceedings and Decisions
First Instance[2]
Triple Point commenced proceedings in the Technology and Construction Court claiming payment on unpaid invoices. PTT counterclaimed for LDs for delays up to the point of termination as well as for its other losses arising from the termination.
Triple Point’s claim was dismissed. PTT was awarded its costs of termination as well as LDs for delays incurred prior to termination, on the basis that the LDs provision applied to both Phases 1 and 2 up to the point of termination.
Court of Appeal[3]
Triple Point appealed and PTT cross appealed. The Court of Appeal, relying on a House of Lords judgment[4], decided that the phrase “up to the date PTT accepts such work” meant that the clause did not apply in circumstances where Triple Point did not complete – and so PTT could not accept – the works. As such, the court found that while PTT was entitled to LDs in respect of the completed Phase 1 works, it was not entitled to LDs for the Phase 2 works which had not been completed or accepted.
The Supreme Court
PTT then appealed to the Supreme Court. The main issue it needed to consider was whether LDs were payable in respect of works which were not completed or accepted prior to termination. Lady Arden, who delivered the lead judgment, found that the Court of Appeal’s approach was “inconsistent with commercial reality and the accepted function of liquidated damages” which is to provide a “predictable and certain” remedy. If the right to accrued LDs is simply lost in the event of termination, this overturns the accepted position that accrued rights and liabilities survive termination.
In respect of the language of the clause, it was held that the parties had included the words “up to the date of acceptance” out of caution, to remove any question that LDs were payable after acceptance, but that this was not a pre-condition of Triple Point’s liability. Accordingly, the Supreme Court ruled that PTT was entitled to LDs for any delay that had accrued up to the date of termination, whether or not that work had been completed.
Comment
LDs are a standard feature of construction contracts, conferring predictability and certainty to both employer and contractor. As noted by Lord Leggatt, the approach taken by the Court of Appeal could have created a perverse incentive for a contractor in delay to not complete works in order to avoid liability for LDs. As such, the Supreme Court’s decision is a welcome restatement of the general law that LDs cease to accrue on termination, that thereafter general damages apply, and that the accrued rights and liabilities of parties – including in respect of LDs – survive termination.
As well as providing clarity on this issue, this case serves as a further reminder that contractual clauses should always be drafted in plain language that makes the intention and application of the clauses clear, because if a clause is contested then interpretation is key.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email
Clare Mendelle is a Professional Support Lawyer, Francesca Gallagher is a Paralegal and James Goldthorpe is a Paralegal at Sharpe Pritchard LLP.
For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email
|
Click here to view our archived articles or search below.
|
|
ABOUT SHARPE PRITCHARD
We are a national firm of public law specialists, serving local authorities, other public sector organisations and registered social landlords, as well as commercial clients and the third sector. Our team advises on a wide range of public law matters, spanning electoral law, procurement, construction, infrastructure, data protection and information law, planning and dispute resolution, to name a few key specialisms. All public sector organisations have a route to instruct us through the various frameworks we are appointed to. To find out more about our services, please click here.
|
|
OUR RECENT ARTICLES
April 30, 2026
The meaning and application of “freedom of speech” within the lawGeorge McLellan and Olivia Dawson represented the Free Speech Union in intervening to present written submissions to the Court concerning the meaning and application of “freedom of speech within the law”.
April 30, 2026
High Court rules on the service of local authority decision notices by emailThe High Court has confirmed that email service of statutory notices and decisions by local authorities is valid and effective on delivery, irrespective of whether the email is seen by the person concerned. Chloe McQuillan, Olivia Peake, and Amy Dann explain what you need to…
April 24, 2026
Post award modifications: Analysis of the “Modifications Claim” in TNLC v The Gambling Commission [2026] EWHC 891 (TCC)Nicola Sumner and Beatrice Wood consider the recent judgment which included claims in relation to the conduct of the procurement process (the “Process Claim”) and a challenge to post award modifications made to the Fourth UK National Lottery Licence (the “Modifications Claim”).
April 24, 2026
Separation of Powers in Wales: Is there a duty to consult before introducing a Bill into the Senedd Cymru?Oliver Dickie and Olivia Peake consider the judgment in R (The Greyhound Board of Great Britain Limited) v The Welsh Ministers [2026] EWHC 670 (Admin).
|
|
OUR KEY LOCAL GOVERNMENT CONTACTS
|
||
|
Partner 020 7406 4600 Find out more |
||
|
Partner 020 7406 4600 Find out more |
||
|
Rachel Murray-Smith Partner 020 7406 4600 Find out more |
||
|
|
||
|
Jo Pickering Partner 020 7406 4600 Find out more |
||
|
|
||
|
Emyr Thomas Partner 020 7406 4600 Find out more |
||
|
|
||
|
Gemma Duncan Partner 020 7406 4600 Find out more |
||
|
|
||
|
Simon Kiely Partner 020 7406 4600 Find out more |
||








Catherine Newman




