- Details
The Court of Appeal decides on JCT DB 2016 termination provisions
Helen Arthur provides an update on an important Court of Appeal ruling in a case concerning the proper construction of termination provisions in a JCT 2016 Design & Build form of Contract.
The Court of Appeal handed down its Judgment last week in Providence Building Services Limited v Hexagon Housing Association Limited [2024] EWCA Civ 962 overturning the decision of the Technology and Construction Court (TCC) in relation to the proper construction of termination provisions in a JCT 2016 Design & Build form of Contract.
Facts
In February 2019 Hexagon and Providence entered into an amended JCT Design & Build 2016 contract (for the construction of a number of buildings in Purley for the sum of £7.2m (the “Contract”). The Contract provided for interim payments to be made by Hexagon with the final date for payment for each Interim Payment being 21 days from its due date.
In December 2022 Hexagon failed to pay the notified sum by the final date for payment and Providence issued a specified default notice relying on clause 8.9.1 of the Contract. The notified sum was eventually paid by Hexagon some 13 days later.
In April 2023 Hexagon failed to pay the notified sum by the final date for payment so Providence issued a termination notice relying on clause 8.9.4 of the Contract, arguing that Hexagon had repeated its specified default. Hexagon paid the notified sum under a week later. Hexagon brought arguments in relation to the validity of the termination notice and accepted what it considered was a repudiatory breach by Providence.
The parties referred the dispute to adjudication resulting in the adjudicator deciding in Hexagon’s favour. Providence then commenced Part 8 proceedings in the TCC for a declaration in respect of the proper construction of clause 8.9 of the Contract.
Clause 8.9 of the Contract states:
“8.9.1 If the Employer:
.1 does not pay by the final date for payment the amount due to the Contractor in accordance with clause 4.9 and/or any VAT properly chargeable on that amount…the Contractor may give to the Employer a notice specifying the default or defaults (a ‘specified’ default or defaults).
8.9.3 If a specified default or a specified suspension event continues for 28 days from the receipt of notice under clause 8.9.1 or 8.9.2, the Contractor may on, or within 21 days from, the expiry of that 28 day period by a further notice to the Employer terminate the Contractor’s employment under this Contract.
8.9.4 If the Contractor for any reason does not give the further notice referred to in clause 8.9.3, but (whether previously repeated or not):
.1 the Employer repeats a specified default…then, upon or within 28 days after such repetition, the Contractor may by notice to the Employer terminate the Contractor’s employment under this Contract.” [Emphasis added]
TCC Decision
The question to be decided was whether a right to terminate under clause 8.9.3 of the Contract needed to accrue before clause 8.9.4 could be relied on.
The Judge noted that the principal task was to ascertain the natural and ordinary meaning of clauses 8.9.3 and 8.9.4. Clause 8.9.3 was straightforward: the clause gave the Contractor the choice whether or not to serve a notice to terminate and that termination would require the Contractor to ‘take an active step’ in serving the termination notice. Neither the words ‘for any reason’ nor clauses 8.9.3 and 8.9.4 as whole envisaged, that a Contractor can give a valid clause 8.9.4 notice in circumstances where the right to give a clause 8.9.3 notice has never arisen—i.e. where the specified default has been cured within the 28-day period.
Providence’s termination notice was found to be invalid.
Court of Appeal decision
The Court of Appeal considered this differently and stated that: “the words ‘for any reason’ remain broad enough to catch a case where the reason why the further notice may not be given is that there is no accrued right to give it. On that approach, the conditional words of Clause 8.9.3 are satisfied even where the Contractor had no accrued right to give the further notice referred to in Clause 8.9.3…”
The Court went on to state that the TCC decision, in particular the references to the Contractor needing to ‘take an active step” not to give a clause 8.9.3 notice, to be unhelpful as it distracts “attention from the true meaning of the words that fall to be interpreted. The question to be addressed is simply and only whether the Contractor has given further notice, not whether the giving (or not) of the notice can be given the (non-contractual) description of being the result of a decision or the taking of an active step.”
Therefore, the Court found in favour of Providence and overturned the TCC decision.
Points to note
- Termination provisions and the related notice requirements always need to be approached with caution and considered carefully.
- The Court noted that this approach now means that in terms of risk profile as between the parties the Employer is on “thinner ice from the outset”. As such, Employers should keep an even closer eye on contractual timeframes and events which could give rise to a ‘specified default’.
Helen Arthur is a Senior Professional Support Lawyer at Sharpe Pritchard LLP.
For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.
This video is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email
|
Click here to view our archived articles or search below.
|
|
ABOUT SHARPE PRITCHARD
We are a national firm of public law specialists, serving local authorities, other public sector organisations and registered social landlords, as well as commercial clients and the third sector. Our team advises on a wide range of public law matters, spanning electoral law, procurement, construction, infrastructure, data protection and information law, planning and dispute resolution, to name a few key specialisms. All public sector organisations have a route to instruct us through the various frameworks we are appointed to. To find out more about our services, please click here.
|
|
OUR RECENT ARTICLES
November 20, 2025
Strengthening the standards and conduct framework for local authorities in EnglandJames Berry offers his insight into how the proposed changes to standards and conduct rules will affect local authorities.
November 04, 2025
Procuring and operating open frameworks under the Procurement Act 2023Chantelle Pink offers advice to authorities on open frameworks and how to procure them.
October 31, 2025
Building Solar – 5 Top Tips for Solar Farm Construction ContractsSolar farm construction contracts are in focus following fascinating insights into the continuing global uptake and expansion of renewables, and particularly solar, within the 2025 mid-year report of Ember, a global energy think tank.
October 22, 2025
The ‘Hillsborough Bill’ – Voices for victims or just more lip service?Jonathan Blunden, Alastair Lewis and Conrad Turnock talk through the recently introduced 'Hillsborough' Bill, aimed at giving victims of state injustice a meaningful voice.
|
|
OUR KEY LOCAL GOVERNMENT CONTACTS
|
||
|
Partner 020 7406 4600 Find out more |
||
|
Partner 020 7406 4600 Find out more |
||
|
Rachel Murray-Smith Partner 020 7406 4600 Find out more |







Catherine Newman
