- Details
No overlap between substance and jurisdictional issues
Clare Mendelle and James Goldthorpe examine the implications of Ex Novo Limited v MPS Housing Limited [2020] EWHC 3804 (TCC)]
Case Background
In this case Ex Novo sought to enforce an adjudicator’s decision in its favour. MPS Housing, resisting enforcement, argued that the adjudicator did not have jurisdiction because the adjudication reference related to multiple contracts and an adjudicator does not (without the parties’ agreement) have jurisdiction to determine disputes under multiple contracts. The adjudicator had addressed the single vs multiple contracts issue and determined that the allegedly separate contracts were in fact a single contract that was subsequently varied.
Questions for the Judge
The two questions for the TCC judge were:
- Whether the adjudicator had jurisdiction. This turned on whether there was a single contract with multiple instructions or multiple contracts.
- Whether the adjudicator’s decision that there was a single contract was a decision he had jurisdiction to make. If it was, then the decision would be enforceable even if incorrect.
Reasoning
After considering the authorities, the judge determined that the proper approach to take would depend on whether the reference to the adjudicator necessarily involved the adjudicator having jurisdiction to determine jurisdiction. In other words, if that decision was an integral part of the substantive reference then the decision was unchallengeable. However, if that decision was only a preliminary matter to be decided before determining the reference proper, then the decision was challengeable. As such, the court needed to look at all of the circumstances and decide whether the reference entitled the adjudicator to determine jurisdiction as part of the substantive reference, or whether it was a necessary preliminary matter.
Decision
While the adjudicator did have to decide whether there was a single contract or multiple contracts, he did not have to answer that question in order to make a decision on the substantive issue between the parties, which was regarding payment and the effect of the absence of a pay less notice from MPS Housing. Rather, he had to answer the question for the purpose of deciding whether he had jurisdiction and should proceed with the adjudication. As such the decision was a preliminary matter and, therefore, non-binding and potentially challengeable.
The judge then considered the single vs multiple contracts issue, and whether MPS Housing had a real prospect of defeating the argument that there was a single contract. Looking at the parties’ intentions and their dealings, he considered that there was no real prospect of finding that there were multiple contracts. Accordingly, the adjudicator’s decision that the reference to adjudication was under a single contract was correct, and the decision was enforceable.
Commentary
While substance and jurisdiction were not found to be overlapping in this case, there may be instances where they are. As such, courts will need to consider the purpose for which it was necessary for an adjudicator to make a particular decision.
Clare Mendelle is a professional support lawyer and James Goldthorpe a paralegal at Sharpe Pritchard LLP
For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email
|
Click here to view our archived articles or search below.
|
|
ABOUT SHARPE PRITCHARD
We are a national firm of public law specialists, serving local authorities, other public sector organisations and registered social landlords, as well as commercial clients and the third sector. Our team advises on a wide range of public law matters, spanning electoral law, procurement, construction, infrastructure, data protection and information law, planning and dispute resolution, to name a few key specialisms. All public sector organisations have a route to instruct us through the various frameworks we are appointed to. To find out more about our services, please click here.
|
|
OUR RECENT ARTICLES
January 21, 2026
White Paper or White Flag? And the Big Red LinesSteve Gummer shares his insight into what Defra's new 'New Vision for Water' and the test for deliverability actually mean for the water sector in England.
January 15, 2026
Data Centres Enter the NSIP RegimeJames Goldthorpe and Emyr Thomas explain the UK government facilitating data centre developments through the NSIP regime and how stakeholders, including host local authorities, can prepare.
January 15, 2026
Scope of Judicial Review in a Contractual ContextOlivia Dawson and Olivia Peake provide an update on recent case law and how it reflects on the scope of judicial review in a contractual context.
January 12, 2026
Local authority leisure services: The agency modelJames Berry explains the tax context, the practical implications and key issues to address when implementing or modifying arrangements.
|
|
OUR KEY LOCAL GOVERNMENT CONTACTS
|
||
|
Partner 020 7406 4600 Find out more |
||
|
Partner 020 7406 4600 Find out more |
||
|
Rachel Murray-Smith Partner 020 7406 4600 Find out more |







Catherine Newman
